Paving Project

Posted on Apr 19, 2018

April 30th will begin a new paving project.  We will be paving South Indianapolis Road to Samuel Moore Parkway all the way to State Road 67.  Also scheduled to be paved is Bridge Street from Indianapolis Road to Landersdale Road.  The schedule will be as follows.

Monday April 30th –  Milling Bridge Street from Landersdale to 67

Tuesday May 1st – Milling Bridge Street from 67 to Indianapolis Road

Tuesday May 1st: – Paving Bridge Street from Landersdale to 67

Wednesday May 2nd – Milling Samuel Moore Parkway

Wednesday May 2nd – Paving remaining approaches on the east portion of Bridge St. and the west portion of Bridge Street from 67 to Indianapolis Rd.

Thursday May 3rd – Milling the remainder of Samuel Moore Parkway and Indianapolis Rd

Thursday May 3rd – Paving Samuel Moore Parkway

Friday May 4th – Paving the remainder of Samuel Moore Parkway and Indianapolis Rd

Monday May 7th – Stone shoulder where needed

Monday May 7th – Thermoplastic Striping at intersections with 67

Tuesday May 8th – Thermoplastic Striping

Wednesday May 9th – Thermoplastic Striping

Thursday May 10th – Thermoplastic Striping

Thursday May 10th – Traffic Loops

Friday May 11th  – Thermoplastic Striping

Friday May 11th – Traffic Loops